The LRT lines 2 and 4 – the newly-expanded Trillium line and airport spur – are now about two weeks into the 8-10 week testing and commissioning phase. Some time within that period, the lines will go into a two-week trial running when they must perform virtually flawlessly before the contractor turns them over to the City and the lines go into service. Last Thursday, Council and the media received a briefing on progress, and I thought that would be helpful to share here. To view the presentation, click here.