Scott St. Widening Update: week of September 21st, 2015

You are here

Last week

  • Asphalt was placed on Scott St. between Carruthers Ave. to Holland Ave. Monday, Sept. 14th and Tuesday, Sept. 15th.
  • Two westbound lanes currently open to traffic on Scott St. from Bayview Rd. to Holland Ave.
  • Curb-side catchbasin installation complete on Scott St. between Tunney’s Pasture to Smirle at the west limit of widening work.

This week

  • Road excavation and gravel placement for widening underway from Holland Ave to Smirle Ave.

Multi-Use Pathways

  • Topsoil placement underway on embankment constructed for multi-use pathway #5 – south-side of Scott St between Bayview Station pedestrian crossing and O-Train line.
  • Water service installation to start this week under multi-use pathway #3 – track removal complete – south-side of Scott St. between Bayview Road and O-Train line.
  • Clearing and sub-grade preparation started for multi-use pathway #2 – north side of Scott St. between Bayview Road and O-Train Trillium Line.

****Please note: all above mentioned construction dates are weather dependent and subject to change.

Posted September 23, 2015