We've received the following updates on Scott Street widening and MUP construction.
Scott St. widening update
Rogers’ relocations completed to west limits of Scott St. widening area - see photo #81625 (between Holland and Smirle)
Catchbasins, curb, and roadway granular are in place for the widening from Carruthers to Holland
Hot Mix asphalt placement (Paving) Monday, Sept. 14th Carruthers to Holland
By end of day tomorrow (Sept. 15th) widening complete with exception of intersections from Bayview Road to Holland
Widening work to begin between Holland and Smirle to start Sept. 15th or 16th.
MUP construction update
The embankment and sub-grade has been constructed for MUP no. 5 – south-side of Scott St between Bayview Station pedestrian crossing and O-Train line (refer to attached photo).
Tree and shrub clearing was completed last week to allow for construction of MUP no. 3 – south-side of Scott St. between Bayview Road and O-Train line (refer to attached photo).
Tree and shrub clearing was completed last week to allow for construction of MUP no. 2 – sub-grade construction started – north side of Scott St. between Bayview Road and O-Train line (refer to attached photo).
***Please note that all dates listed above may change due to weather or other unforeseen circumstances.