Scott Street Detour Construction Public Webinar July 27

You are here

Construction began this week on the Scott Street bus detour, part of the ongoing Stage 2 LRT project. Making these changes along Scott Street will allow OC Transpo to operate its buses while crews are constructing the LRT in the Transitway trench.

To that end, our office is holding a public webinar on July 27at 7pm so you can learn what to expect during the construction of the detour and beyond.  


When: Jul 27, 2021 07:00 PM Eastern Time (US and Canada)
Topic: Scott Street Detour Construction Webinar

Please click the link below to join the webinar:
https://us02web.zoom.us/j/82343435103
Passcode: 938495

 

Understanding that you may have several questions about the schedule before this meeting is held, our LRT Stakeholder Relations team has put together this schedule of what to expect in the coming months.

Churchill to Island Park (June 30th to July 7th)

July 5th and 6th

South side bulb-out removals

July 7th

Temporary paving

Traffic shift to south side of right-of-way

 

July 21st to September 20th (south side)

July 21st to August 4th

Asphalt removals

July 22nd to August 5th

Granular placement + sub drains

August 6th to 16th

Install temporary bus platforms

August 6th to 26th

Concrete flatworks

August 17th to 20th

Pave curb strip

August 23rd to 27th

 

Pave cycle track

August 30th to September 20th

 

Landscaping

 

Churchill to Lanark (July 8th to August 26th)

July 8th to July 14th

North side

Asphalt removal

Granular placement

July 15th

North side

Asphalt widening

Temporary shift to north side of right-of-way

July 15th to August 26th

Westboro Station civil works

July 16th to July 23rd

South side

Catch basin relocation

July 26th to July 28th

South side

Hydrant relocations

 

Lanark to Oakdale (July 7th to August 25th)

July 7th to 27th

North side

Traffic plant relocation

July 16th to 27th

North side

Asphalt removal

Granular placement + sub drain

July 19th

North side

Catch basin relocations

July 28th to August 11th

North side

Concrete flatworks

August 12th to 13th

North side

Pave widening

August 16th

North side

Traffic shift

August 16th to 25th

North side

Landscaping

August 17th to 19th

South side

Storm line install

August 20th to 23rd

South side

Catch basin relocation

 

Oakdale to Caroline (July 13th to October 6th)

July 13th to August 3rd

North side

Traffic plant relocation

July 28th to August 3rd

North side

Asphalt removals

July 29th to August 4th

North side

Granular placement + sub drain

August 5th to 11th

North side

Catch basin relocations

August 12th to 23rd

North side

Concrete flatworks

August 24th to 26th

Pave widening on north side

August 27th to September 3rd

 

Landscaping (north side)

Asphalt removals (south side)

August 31st to September 22nd

South side

Traffic plant relocation

September 7th to 14th

Granular placement

September 15th to 17th

South side

Catch basin relocations

September 23rd to 28th

South side

Concrete flatworks

September 19th and 30th

South side

Pave cycle track

October 1st to 6th

South side

Landscaping

 

 

 

We hope to see you on the 27th.