We've received the following update on Scott Street construction from the City:
Scott St. widening and Multi-Use Pathways update
Last week:
• Widening work completed Bayview to Holland with exception of intersections
• Road construction excavation and gravel placement complete Tunney’s Pasture to Smirle Ave.
This week:
• Curb installation beginning from Tunney’s Pasture and heading west - Sept. 28th
• Intersection clearing and pole placement starting at Parkdale and Bayview Road Sept. 28th
• Merton St. connection starting Sept. 28th
Multi Use Pathway:
• MUP #2 (north side of Scott St west of Bayview Station) prepared and ready for asphalt placement. Track removed north of Bayview Station.
• MUP #5 (south side of Scott St east of Bayview Station) prepared and ready for asphalt placement
• MUP #3 (south side Scott St west of Bayview Station) cordoned off and ready for watermain installation. Track removed for watermain installation and MUP construction (see picture).
***Please note that all above mentioned dates are subject to change as construction activities are weather dependant.