Scott Street widening update

  • Concrete curb and sidewalk installation completed at all intersections
  • Asphalt paving overlay complete with pavement marking between Pinhey Street and 100m west of City Centre Avenue
  • Temporary Transitway is ready, except for signage and minor pavement marking, between Empress Avenue and Merton Street

Work remaining

  • Asphalt for north-side widening at curb radii for Tunney’s Pasture entrance, Holland, Parkdale, Hinchey, and Carruthers
  • Asphalt overlay existing Multi Use Pathway from Smirle Avenue to Bayview Road
  • Final West Transitway Detour pavement markings between Smirle Avenue and Merton Street
  • Signals to be commissioned at City Centre Avenue and decommissioned at the Bayview pedestrian crossing by November 27th
  • Signals at Merton Street connector to be scheduled sometime before the end of December 2015
  • Street light power connections remain for Multi Use Pathways #2 and #3
    • #2 - north of Scott Street between Bayview Road and Station
    • #3 – south of Scott Street/north of Tom Brown Arena, between Bayview Road and the Trillium Line corridor