This flyer will be circulated this weekend to residents in the proximity of Cleary and Dominion:
Dear Resident:
This notice is to advise that, as part of future cut and cover construction of the Stage 2 Confederation Line West extension, crews are beginning preparatory activities on the Sir John A. Macdonald Parkway between Dominion Avenue and Cleary Avenue.
This preparatory work is scheduled to begin the week of May 13 and continue into 2020, which will allow cut and cover construction to safely occur on the south side of the Sir John A. Macdonald Parkway without interfering with traffic. All work is being done in accordance with the regulatory requirements for the project, and with planning participation and approval from the NCC.
KEY ACTIVITIES AND TIMELINE
Phase 1: Beginning week of May 13 through June*
Site mobilization and area clearing along the centre boulevard (median) to the north of Sir John A. Macdonald Parkway. This work includes:
This work is scheduled to occur during typical daytime construction hours between 7am and 10pm Monday to Saturday, and between 9am to 10pm on Sunday’s and holidays.
Area clearing is in preparation for construction of temporary traffic lanes as part of Phase 2.
Phase 2: June through September*
Temporary traffic lane construction and utility relocation will occur to the north of Sir John A. Macdonald Parkway. Once completed, traffic will be shifted to the north side of Sir John A. Macdonald Parkway in preparation for work in the median.
Phase 3: September through December (and into 2020)*
Temporary traffic lane construction and utility relocation will occur in the median of Sir John A. Macdonald Parkway. Once completed, all traffic will be shifted to the north side of Sir John A. Macdonald Parkway that will allow cut and cover construction to safely occur on the south side without interfering with traffic.
Phase 4: September through December (and into 2020)*
Area clearing and tree removal will occur along the south side of Sir John A. Macdonald Parkway in preparation for cut and cover construction. Once again, all phases of work will be compliant with regulatory requirements and with approval with the NCC.
The underground light rail transit (LRT) system in this area will require in-trench construction to the south of Sir John A. Macdonald Parkway. The above-ground area will be cleared so that crews can begin the underground work where the future train will operate.
*Please note paving and other roadworks are weather dependent and dates will be subject to change.
HOURS OF WORK
The project team anticipates most activity to be scheduled during typical daytime construction hours. If nightwork is required to assist the travelling public, appropriate notice will be provided.
ANTICIPATED IMPACTS
Pedestrians and Cyclists
Pedestrian and cycling access along Sir John A. Macdonald Parkway will be maintained. Temporary crossings will be implemented along the construction corridor and pedestrians and cyclists should use extra caution as traffic patterns change.
Motorists
Traffic will be maintained although delays may occur at times. Intermittent daytime off-peak lane closures will be required at times. Motorists should be aware of and adhere to traffic control signage, posted speed limits and traffic control personnel.
Residents and Businesses
Noise and temporary disruption are not anticipated to be significant during this work. Access to and from properties will be maintained although local traffic delays may occur at times.
The safety of workers and the public is paramount, and we thank you for your patience during construction.
WHAT’S NEXT
In early 2020, crews will complete any remedial work in Phase 4 and begin cut and cover activity in this area. More information will be available once confirmed later this year. Please stay connected with our team as we report on our progress and provide our 2020 construction look-ahead.
For further information about this project, please contact the City’s representative:
Damon Berlin
Stakeholder Relations, Rail Construction Program, City of Ottawa
Email: damon.berlin@ottawa.ca
Phone: 613-580-2424, ext. 12764
OR
Email: stage2@ottawa.ca
Phone: 3-1-1