Scott Street construction update - September 28

You are here

We've received the following update on Scott Street construction from the City:

Scott St. widening and Multi-Use Pathways update

Last week:
•    Widening work completed Bayview to Holland with exception of intersections 
•    Road construction excavation and gravel placement complete Tunney’s Pasture to Smirle Ave.

This week:
•    Curb installation beginning from Tunney’s Pasture and heading west - Sept. 28th 
•    Intersection clearing and pole placement starting at Parkdale and Bayview Road Sept. 28th
•    Merton St. connection starting Sept. 28th 

Multi Use Pathway:
•    MUP #2 (north side of Scott St west of Bayview Station) prepared and ready for asphalt placement. Track removed north of Bayview Station.
•    MUP #5 (south side of Scott St east of Bayview Station) prepared and ready for asphalt placement
•    MUP #3 (south side Scott St west of Bayview Station)  cordoned off and ready for watermain installation. Track removed for watermain installation and MUP construction (see picture).

***Please note that all above mentioned dates are subject to change as construction activities are weather dependant.

Posted September 28, 2015